Construction Progressing on Fuel Ammonia Facilities for JERA's Hekinan Thermal Power Plant
NQ Score
56/100
AI analysis data is not yet available.
Frequently Asked Questions
- Q: Which companies received the order for the EPC of the fuel ammonia storage tanks?
- A: IHI Plant Corporation, Taisei Corporation, and Chubu Plant Service Co., Inc. received the order.
- Q: What is the total capacity of the four fuel ammonia storage tanks being constructed?
- A: The total capacity of the four fuel ammonia storage tanks is 160,000 tons.
- Q: When is the start of commercial operation of large-scale ammonia co-firing targeted for?
- A: The commercial operation of large-scale ammonia co-firing is targeted for fiscal year 2029.
- Q: What method was used to raise the outer tank roofs for Unit 1 and Unit 2 as of March 2026?
- A: The outer tank roofs for Unit 1 and Unit 2 were raised using the air-raising method.
- Q: What are the specific responsibilities of Taisei Corporation in this project?
- A: Taisei Corporation is handling the foundation work, containment dikes, and foundations and building work for auxiliary facilities.