Construction Progressing on Fuel Ammonia Facilities for JERA's Hekinan Thermal Power Plant

NQ Score 50/100

AI Summary (NQ-processed)

IHI Plant Corporation, Taisei Corporation, and Chubu Plant Service Co., Inc. have been awarded the EPC (Engineering, Procurement, and Construction) for four fuel ammonia storage tanks (160,000 tons total capacity) and associated facilities for JERA. Construction is underway to enable the start of large-scale ammonia co-firing (20% by heating value) at the Hekinan Thermal Power Plant, aiming for commercial operation in fiscal year 2029 as part of JERA's 'JERA Zero Emission 2050' initiative.

AI analysis data is not yet available.

Frequently Asked Questions

Q: Which companies received the order from JERA Co., Inc. for the Engineering, Procurement, and Construction of the fuel ammonia storage tanks?
A: IHI Plant Corporation, Taisei Corporation, and Chubu Plant Service Co., Inc. received the order for the EPC of the facilities.
Q: What is the total capacity of the four fuel ammonia storage tanks being constructed for the Hekinan Thermal Power Plant?
A: The total capacity of the four fuel ammonia storage tanks being constructed is 160,000 tons.
Q: What target commercial operation date and ammonia co-firing rate are set for this project?
A: The start of commercial operation of large-scale ammonia co-firing (20% by heating value) is targeted for fiscal year 2029.
Q: What construction milestones were completed for the Hekinan Thermal Power Plant ammonia storage tanks as of March 2026?
A: As of March 2026, the outer tank roofs for Unit 1 and Unit 2 have been raised using the air-raising method, and exterior construction is complete.
Q: What are the specific responsibilities of Taisei Corporation in the fuel ammonia storage tanks construction project?
A: Taisei Corporation is handling the foundation work for the ammonia storage tanks, containment dikes construction, and foundations/building work for auxiliary facilities.