Lienchiang County to Terminate Contract for School Project Over 20% Behind Schedule

NQ Score 4/100
N1 Content Completeness 4

AI Summary (NQ-processed)

Lienchiang County Magistrate Wang Chung-ming announced on May 21 that the county government will terminate its contract with the contractor for the Beigan Zhongshan Junior High School relocation project due to poor performance. The project is over 20% behind schedule, with less than 3% progress in over two years. The same contractor is also responsible for a poor-quality road project. Councilors criticized the government for being too lenient, and the government will pursue legal action for breach of contract.

AI Analysis

Frequently Asked Questions

Q: 北竿中山國中遷校工程出了什麼問題?
A: 根據新聞,該工程開工超過2年,但施工進度不到3%,整體進度落後超過20%,屬於嚴重延宕。
Q: 連江縣政府對此將採取什麼行動?
A: 縣長王忠銘表示,因工程進度落後已違反契約,縣府已委請律師,將對承包商提出中止或解除合約,並追究相關的違約與法律責任。
Q: 該承包商是否還涉及其他問題工程?
A: 是的,同一家營造商也承包了「北竿塘后道聯外道路工程」,被議員指責品質低落,路面像「狗皮膏藥」,還破壞了塘后沙灘。
Q: 議員對縣政府的態度為何?
A: 多位國民黨籍議員批評,塘后道聯外道路工程品質低落,且縣府長期縱容廠商任意展延工期,對於工程品質不佳難辭其咎。
Q: 品質不佳的塘后道聯外道路後續如何處理?
A: 縣長王忠銘表示,該工程雖已進入驗收階段,但縣府已委託結構技師公會等第三方協助驗收,並會要求承包商必須負起塘后沙灘的復原責任。